TY - JOUR
T1 - Last planner® system and percent plan complete
T2 - An examination of trade contractor performance
AU - Power, William
AU - Taylor, Darrin
N1 - Publisher Copyright:
© 2019, Lean Construction Institute. All rights reserved.
PY - 2019
Y1 - 2019
N2 - Research Question: What are the project performance differences between Irish construction firms that have adopted Lean thinking and practices and those that have not? Purpose: This study explores Percent Plan Complete (PPC) as part of the application of Last Planner® System (LPS) across two concurrent capital projects in Ireland. It examines commonalities and differences between trade contractors’ PPC, and it identifies areas of improvement for implementation on future projects. Research Method: Mixed-methods approach encompassing critical literature review, site documentation data-analysis, focus groups, and semi-structured purposeful interviews. Findings: Lean Construction-oriented contractor selection, early engagement of trades in the design process, implementation of all functions of LPS, education and training in Lean, increased modularization and prefabrication, and embracing technological advances are posited as areas for focused improvement. Limitations: This study is limited to examination of PPC data from two concurrent Engineering, Procurement, Construction Management, Validation (EPCMV) Projects. Implications: Irish construction firms should adopt Lean thinking and practices to provide added value on capital projects. There is a need for further studies on the PPC performances and reasons for non-completion (RNC) of trade contractors across multiple projects.
AB - Research Question: What are the project performance differences between Irish construction firms that have adopted Lean thinking and practices and those that have not? Purpose: This study explores Percent Plan Complete (PPC) as part of the application of Last Planner® System (LPS) across two concurrent capital projects in Ireland. It examines commonalities and differences between trade contractors’ PPC, and it identifies areas of improvement for implementation on future projects. Research Method: Mixed-methods approach encompassing critical literature review, site documentation data-analysis, focus groups, and semi-structured purposeful interviews. Findings: Lean Construction-oriented contractor selection, early engagement of trades in the design process, implementation of all functions of LPS, education and training in Lean, increased modularization and prefabrication, and embracing technological advances are posited as areas for focused improvement. Limitations: This study is limited to examination of PPC data from two concurrent Engineering, Procurement, Construction Management, Validation (EPCMV) Projects. Implications: Irish construction firms should adopt Lean thinking and practices to provide added value on capital projects. There is a need for further studies on the PPC performances and reasons for non-completion (RNC) of trade contractors across multiple projects.
KW - Ireland
KW - Last Planner System
KW - Lean Construction
KW - Percent Plan Complete
KW - Reasons for Non-Completion
UR - http://www.scopus.com/inward/record.url?scp=85078600400&partnerID=8YFLogxK
M3 - Article
AN - SCOPUS:85078600400
VL - 2019
SP - 131
EP - 146
JO - Lean Construction Journal
JF - Lean Construction Journal
SN - 1555-1369
ER -